Project Update 2020-08-27

RAPID CITY, S.D. – August 26 – Work this week includes curb and gutter installation, driving lane tie-ins, and various items at the west entrance to Founders Park. The east entrance into the Founders Park parking lot is open and the west entrance is closed for construction. The westbound lanes from 12th Street/Founder’s Park Drive to Cross Street are closed and two-way traffic is in the eastbound lanes. There is a 10-foot width restriction though the construction work zone.

Water and storm sewer installation is in progress in the Deadwood Avenue southbound driving lane. Widening and paving the southbound lane of Deadwood Avenue, between Cement Plant Road and Krebs Drive, will follow the water and storm sewer installation. Business access on Omaha Street will remain open at all times. Access to Founders Park will be limited to a single approach. Left-hand turns onto Omaha Street are discouraged to allow for continued flow of traffic. Motorists are asked to be aware of suddenly slowing and merging traffic, changing work zone locations, reduced speeds through the work zone, and construction workers and equipment adjacent to the driving lane.

Omaha Street work on curb and gutter 2020-08-27
Omaha Street work on curb and gutter 2020-08-27
Omaha Street west end of Phase 1 project limits 2020-08-27
Omaha Street west end of Phase 1 project limits 2020-08-27
%d bloggers like this: