RAPID CITY, S.D. – January 6 – Work this week includes backfilling and topsoil placement along curbs and sidewalks and installing temporary pavement markings.

A change in traffic will take place Monday, January 11. Traffic will be in two eastbound lanes and two westbound lanes from 12th Street to Cross Street. The inside lanes will be closed for work in the median. The traffic signal at Cross Street will be active.

The southbound outside lane on Deadwood Avenue, between Cement Plant Road and Krebs Drive is closed. Sidewalk work continues on Deadwood Avenue this week.

There is a 10-foot width restriction though the construction work zone. Business access on Omaha Street will remain open at all times. Motorists are asked to be aware of suddenly slowing and merging traffic, changing work zone locations, reduced speeds through the work zone, and construction workers and equipment adjacent to the driving lane.

Intersection of Cross Street and Omaha Street 2021-01-06
Intersection of Cross Street and Omaha Street 2021-01-06
<span>%d</span> bloggers like this: