Progress Report 2021-03-25

RAPID CITY, S.D. – March 25, 2021 – The Bike Skills Park north of Omaha Street will be temporarily closed April 7 through April 14, 2021, to allow crews to work on a detention pond northeast of the park. The bike path on the south side of the Bike Skills Park will be open but will not provide access to the Bike Skills Park.

Work has begun on the median from the soccer field entrance to 12th Street, which includes the installation of decorative concrete, landscaping, and a pedestrian crossing at Canal Street.

Work continues on sanitary sewer behind the curb on the north side of the Mountain View Road intersection.

Work has also begun on widening the bridge over Rapid Creek. Crews have removed the sidewalk and railing on the north side of the bridge and continue to progress on foundation work.

Removals have begun for storm sewer work on the north side of Omaha Street, from Rapid Creek west to Deadwood Avenue.

Motorists are asked to be aware of suddenly slowing and merging traffic, changing work zone locations, reduced speeds through the work zone, and construction workers and equipment adjacent to the driving lanes. Additional information will be provided as phasing, access, and traffic control changes with the progression of the project.

Excavation work on the median in preparation to install decorative concrete. March 24, 2021 (John Van Beek/Ferber Engineering Company)
Excavation work on the median in preparation to install decorative concrete, landscaping, and a pedestrian crossing at Canal Street.
March 24, 2021 (John Van Beek/Ferber Engineering Company)