Project Update 2022-01-26

RAPID CITY, S. D. – January 26, 2022 – As weather allows surfacing work including concrete paving, panel replacements, and lane tie-ins will continue on Mountain View Drive and west of the Rapid Creek bridge. 

Work continues on the widening of the Rapid Creek bridge toward the south. The bike path that travels under the Rapid Creek bridge is currently closed and is anticipated to remain closed through mid-April 2022.

Motorists are asked to be aware of suddenly slowing and merging traffic, changing work zone locations, reduced speeds through the work zone, and construction workers and equipment adjacent to the driving lanes.

To view the entire scope of the project, with the phasing and traffic control plans as well as weekly updates, please visit the project website https://www.omahastreetreconstruct.com or the project ArcGIS Storymaps at: https://arcg.is/1yqz450. Interested persons can also follow the project on Facebook, “Omaha Street Reconstruction,” and on Twitter, “Omaha Street Reconstruction@FerbEngCo.” The public may leave a message at (605)343-3311 with any questions or concerns regarding this reconstruction project.

Surfacing work at the Mountain View Road Intersection, Omaha Street, Rapid City, South Dakota, Wednesday, January 26, 2022
Surfacing work at the Mountain View Road Intersection, Omaha Street, Rapid City, South Dakota, Wednesday, January 26, 2022
%d bloggers like this: