Project Update 2022-03-24

RAPID CITY, S. D. – March 23,2022 – Surfacing work including panel replacements and lane tie-ins will continue near the Rapid Creek bridge. Grading work and gravel placement continues in the median area east of the Mountain View Drive intersection. Paving of turn lanes and median curb placement will follow.

Work continues on the widening of the Rapid Creek bridge toward the south. The bike path that travels under the Rapid Creek bridge is currently closed and is anticipated to remain closed through mid-April 2022.

Traffic will be placed in the new outside eastbound lanes east of Mountain View Drive early next week. Also, traffic on Mountain View Drive will be placed in the outside lanes to accommodate median work.

Motorists are asked to be aware of suddenly slowing and merging traffic, changing work zone locations, reduced speeds through the work zone, and construction workers and equipment adjacent to the driving lanes.

To view the entire scope of the project, with the phasing and traffic control plans as well as weekly updates, please visit the project website https://www.omahastreetreconstruct.com or the project ArcGIS Storymaps at: https://arcg.is/1yqz450. Interested persons can also follow the project on Facebook, “Omaha Street Reconstruction,” and on Twitter, “Omaha Street Reconstruction@FerbEngCo.” The public may leave a message at (605)343-3311 with any questions or concerns regarding this reconstruction project.

Sidewalk Placement on Omaha Street, in Rapid City, South Dakota, Wednesday, March 23, 2022
Sidewalk Placement on Omaha Street, in Rapid City, South Dakota, Wednesday, March 23, 2022
%d bloggers like this: