Project Update 2022-05-26

RAPID CITY, S.D. – Median, turn lane, and sidewalk work continues west of Deadwood Avenue to east of Mountain View Road. Miscellaneous work continues on the Rapid Creek Bridge.

No changes will be made in the current traffic control throughout the holiday weekend. Work will be suspended from Saturday, May 28, 2022, through Monday, May 30, 2022.

Motorists are asked to be aware of suddenly slowing and merging traffic, changing work zone locations, reduced speeds through the work zone, and construction workers and equipment adjacent to the driving lanes.

To view the entire scope of the project, with the phasing and traffic control plans as well as weekly updates, please visit the project website at: https://www.omahastreetreconstruct.com or the project ArcGIS Storymaps at: https://arcg.is/1yqz450. Interested persons can also follow the project on Facebook, “Omaha Street Reconstruction,” and on Twitter, “Omaha Street Reconstruction@FerbEngCo.” The public may leave a message at 605-343-3311 with any questions or concerns regarding this reconstruction project.

Concrete paving on Omaha Street, Rapid City, South Dakota, Wednesday, May 25, 2022
Concrete paving on Omaha Street, Rapid City, South Dakota, Wednesday, May 25, 2022
%d bloggers like this: