Project Update 2022-06-02

RAPID CITY, S.D. – Median and sidewalk work continues from Sheffer Street to Cross Street. Miscellaneous work continues on the Rapid Creek Bridge.

Motorists are asked to be aware of suddenly slowing and merging traffic, changing work zone locations, reduced speeds through the work zone, and construction workers and equipment adjacent to the driving lanes.

To view the entire scope of the project, with the phasing and traffic control plans as well as weekly updates, please visit the project website at: https://www.omahastreetreconstruct.com or the project ArcGIS Storymaps at: https://arcg.is/1yqz450. Interested persons can also follow the project on Facebook, “Omaha Street Reconstruction,” and on Twitter, “Omaha Street Reconstruction@FerbEngCo.” The public may leave a message at 605-343-3311 with any questions or concerns regarding this reconstruction project.

Placing colored concrete on median east of Mountain View Road intersection, Rapid City, South Dakota, Wednesday, June 1, 2022
Placing colored concrete on median east of Mountain View Road intersection, Rapid City, South Dakota, Wednesday, June 1, 2022

%d bloggers like this: