Project Update 2022-09-01

Pavement markings are anticipated to be complete by the end of this week from 12th Street to Sheffer Street. Miscellaneous work and cleanup continues near the Rapid Creek Bridge. 

A temporary shoulder closure will be in place to accommodate sidewalk drain work east of Mountain View Drive on Omaha Street.

All contract work is expected to be complete by the middle of September.

In the middle of September, modifications to the median barrier on Deadwood Avenue will be made requiring inside lane closures. This work is expected to last approximately two weeks.

Motorists are asked to be aware of suddenly slowing and merging traffic, changing work zone locations, reduced speeds through the work zone, and construction workers and equipment adjacent to the driving lanes.

To view the entire scope of the project, with the phasing and traffic control plans as well as weekly updates, please visit the project website at: https://www.omahastreetreconstruct.com or the project ArcGIS Storymaps at: https://arcg.is/1yqz450. Interested persons can also follow the project on Facebook, “Omaha Street Reconstruction,” and on Twitter, “Omaha Street Reconstruction@FerbEngCo.” The public may leave a message at 605-343-3311 with any questions or concerns regarding this reconstruction project.

Sidewalk Repair, Omaha Street 
Rapid City, South Dakota