  • Project Update 2022-05-19
    RAPID CITY, S.D. – The bike path remains closed under the Rapid Creek Bridge for repairs and will reopen Friday, May 20, 2022. Bike path traffic is detoured in the same manner as previously on the project utilizing Mountain View…
  • Project Update 2022-05-12
    RAPID CITY, S.D. – The bike path remains closed under the Rapid Creek Bridge for repairs and will reopen Saturday, May 14, 2022.  Bike path traffic is detoured in the same manner as previously on the project utilizing Mountain View…
  • Project Update 2022-05-04
    RAPID CITY, S.D. – The bike path will be closed on Monday, May 9, 2022, under the Rapid Creek Bridge for repairs and will reopen Friday, May 13, 2022.  Bike path traffic will be detoured in the same manner as…
  • Project Update 2022-04-28
    RAPID CITY, S.D.- Clean up, landscaping, and miscellaneous work adjacent to the roadway will take place this week west of the Rapid Creek Bridge.  A traffic switch is expected late next week, placing vehicles in the outside lanes to accommodate…
  • Project Update 2022-04-21
    RAPID CITY, S.D. – Work continues on the Rapid Creek bridge, including barrier and sidewalk placement. The bridge deck overlay is scheduled for late next week. Surfacing work, including panel replacements and lane tie-ins, will continue near the Rapid Creek…
  • Project Update 2022-04-14
    RAPID CITY, S.D. – April 14, 2022 – The bike path is scheduled to re-open on April 16th. Work continues on the widening of the Rapid Creek bridge toward the south, including barrier and sidewalk placement. Surfacing work including panel…
  • Project Update 04-07-2022
    RAPID CITY, S.D. – April 6, 2022 – The bike path is scheduled to re-open on April 16th! Work continues on the widening of the Rapid Creek bridge toward the south, including barrier and sidewalk placement. Surfacing work including panel…
  • Project Update 2022-03-30
    RAPID CITY, S.D. – March 30, 2022 – Surfacing work including panel replacements and lane tie-ins will continue near the Rapid Creek bridge. Grading work and gravel placement continues in the median area east of the Mountain View Drive intersection.…
  • Project Update 2022-03-24
    RAPID CITY, S. D. – March 23,2022 – Surfacing work including panel replacements and lane tie-ins will continue near the Rapid Creek bridge. Grading work and gravel placement continues in the median area east of the Mountain View Drive intersection.…
  • Project Update 2022-03-16
    RAPID CITY, S.D. – March 16, 2022 – Surfacing work including concrete paving, panel replacements, and lane tie-ins will continue near the Rapid Creek bridge and on the south side of the Deadwood Avenue intersection. Grading work is scheduled to…