  • Project Update 2022-09-09
    Miscellaneous cleanup and tree replacement will continue throughout the project with all work expected to be complete by September 30th.  In the middle of September, modifications to the median barrier on Deadwood Avenue will be made requiring inside lane closures.…
  • Project Update 2022-09-01
    Pavement markings are anticipated to be complete by the end of this week from 12th Street to Sheffer Street. Miscellaneous work and cleanup continues near the Rapid Creek Bridge.  A temporary shoulder closure will be in place to accommodate sidewalk drain…
  • Project Update 2022-08-26
    RAPID CITY, S.D. – Pavement markings and sign installation from 12th Street to Sheffer Street continue. Seeding, miscellaneous work, and cleanup continues throughout the project.  Temporary lane closures will be in place through next week near the Rapid Creek Bridge to…
  • Project Update 2022-08-18
    RAPID CITY, S.D. – Pavement markings and sign installation from 12th Street to Sheffer Street are anticipated to be complete this week. Landscaping, soil stabilization, miscellaneous work, and cleanup continues throughout the project.  Temporary lane closures will be in place this…
  • Project Update 2022-08-11
    RAPID CITY, S.D. – With the Sturgis Motorcycle Rally taking place this week, please use extreme caution while driving through the construction area and watch for motorcycles. Pavement markings and sign installation from 12th Street to Sheffer Street are anticipated…
  • Project Update 2022-08-05
    RAPID CITY, S.D. – Lane closures will continue to shift daily to allow for pavement joint sealing, pavement markings, and sign installation from 12th Street to Sheffer Street.  The entire roadway will be swept Friday, Aug. 5th.  Landscaping, soil stabilization,…
  • Project Update 2022-07-28
    RAPID CITY, S.D. – Lane closures will continue to shift daily to allow for pavement joint sealing, pavement markings, and sign installation from 12th Street to Sheffer Street. Landscaping, soil stabilization, miscellaneous work, and cleanup continues throughout the project.  All…
  • Project Update 2022-07-21
    RAPID CITY, S.D. – Lane closures will continue to shift daily to allow for pavement joint sealing, pavement markings, and sign installation from 12th Street to Sheffer Street. This work is anticipated to be completed by the end of July.…
  • Project Update 2022-07-14
    RAPID CITY, S.D. – Lane closures will continue to shift daily to allow for pavement smoothness grinding, joint sealing, pavement markings, and sign installation from 12th Street to Sheffer Street. This work is anticipated to be completed by the end…
  • Project Update 2022-07-07
    RAPID CITY, S.D. – Lane closures will shift daily to allow for pavement smoothness grinding, joint sealing, pavement markings, and sign installation from 12th Street to Sheffer Street. This work is anticipated to be completed by the end of July.…